GTL phase 3 project successfully completed

Koole Terminals in Pernis has granted MOH Service the GTL phase 3 which has been completed successfully. The GTL phase 3 project was a brownfield project during which the terminal has remained in operation as much as possible and down time was restricted to the minimum necessary. MOH Service built and installed a process manifold. During two stops the remaining connections of the new manifold where connected to the live system. Down time for the connections of the manifold could be reduced to one week only. The complete project has been completed successfully, within the timeframe agreed and with zero incidents.